This job for Senior M&E QS seeking work in Marbella was posted on 15/5/2008 3:30:09 PM by lashe
< language=>
>
Hi,
I''m a Senior Building Services Quantity Surveyor currently living and working in the UK for a multinational building services company
I am looking to move to Marbella or anywhere in the Malaga area.
If my CV below is of interest please get in touch
PERSONAL DETAILS
Address: 77 Ebrook Road, Sutton Coldfield, West Midlands, B72 1NU
Email: lashe@blueyonder.co.uk Mobile: 07918 652 117
DOB: 19 March 1980 Age: 28
Status: Single Nationality: English
PERSONAL STATEMENT
As an experienced Senior M&E Building Services Quantity Surveyor with an engineering and design background, my abilities to obtain a complete and focused understanding of a project combined with high levels of financial control and foresight could be utilised to enable a company to achieve its goals
Active and potential clients will benefit from detailed levels of financial reporting covering all aspects of the contract, along with a learned knowledge of value engineering exercises and the meticulous management of their million-pound accounts, allowing long-lasting relationships to be formed.
EMPLOYMENT
|
Senior M&E Quantity Surveyor, Balfour Kilpatrick Ltd, West Region, Birmingham
20 October 2003 Present (www.balfourkilpatrick.com)
BK Ltd provide a complete installation solution for M&E building service, working for a main-contractor or direct for the client acting as main-contractor, from base design through to handover and maintenance services
Specialist sub-contractors are utilised for the majority of works with BK controlling the management side of the installations, combined with a detailed building knowledge with estimating, design services, engineering and innovation, cost monitoring and health and safety
(please refer to page 3 for a more detailed project specific history)
Key Achievements:
o Achieved a framework agreement with a smaller number of sub-contractors based upon performance, H&S and financial aspects to achieve a more focused service
o Redesign of all reporting formats and monitoring to enable close control systems
o Successful completion of a number of large projects working under NEC 3, Dom 2 and JCT 98/2005 DB Sub contracts
|
|
|
EMPLOYMENT
|
Senior M&E Quantity Surveyor, Balfour Kilpatrick Ltd, West Region, Birmingham
20 October 2003 Present (www.balfourkilpatrick.com)
BK Ltd provide a complete installation solution for M&E building service, working for a main-contractor or direct for the client acting as main-contractor, from base design through to handover and maintenance services
Specialist sub-contractors are utilised for the majority of works with BK controlling the management side of the installations, combined with a detailed building knowledge with estimating, design services, engineering and innovation, cost monitoring and health and safety
(please refer to page 3 for a more detailed project specific history)
Key Achievements:
o Achieved a framework agreement with a smaller number of sub-contractors based upon performance, H&S and financial aspects to achieve a more focused service
o Redesign of all reporting formats and monitoring to enable close control systems
o Successful completion of a number of large projects working under NEC 3, Dom 2 and JCT 98/2005 DB Sub contracts
|
|
Electrical Estimator and Design Engineer, Countrywide Electrical Services Ltd, Birmingham
November 2001 October 2003 (www.countrywideelectricalsvs.com)
Working from architectural layouts to achieve a fully functioning design and installation, reporting an auditable costing for the project initially for an estimate breakdown presented to the client and translated to a working quantified schedule of rates
Projects ranged from leisure installations, industrial warehouses, commercial and domestic complexes
|
Electrical Estimator and Design Engineer, Hamilton Reid Ltd, Stoke-on-Trent
October 1999 November 2001
Installations varied from commercial buildings (French Embassy, London), hospitals, broadcasting (BBC)
This role provided a major challenge of creating an electrical division from scratch with minimal support, including liaising with clients, receipt of tenders, forming supply chains with suppliers and sub-contractors, monitoring material purchases and handover to installation team
My role also included the onsite support to the Contracts team in the form of labour supervision and liaison with electrical sub-contractors
|
Trainee Mechanical and Electrical Design Engineer, Emec Ltd, Birmingham
June 1998 October 1999
Nationwide M&E consultancy practice specialising in leisure installations
Trainee Draughtsman, Tilbury Douglas Plc, Birmingham
September 1997 June 1998
Major nationwide civils contractor
|
|
|
|
KEY SKILLS
|
Technical Skills
o Data Analysis
o Microsoft Office, MS Project and AutoCAD
|
|
Personal Skills
o Management clients requirements and staff
o Flexibility
o Problem solving abilities
o Good communication, record keeping and reporting skills
o Leadership team motivator
|
|
|
|
EDUCATION
|
HNC Contract Management
(ECA approved)
HNC Electrical Building Services Engineering
ONC Mechanical Building Services Engineering
|
|
CPD Negotiating Skills
(2 day external course)
CPD Interpersonal Skills
(3 day external course)
CPD Management Skills
(1 day external course)
|
|
|
|
2006 - 2008
Loughborough College, Loughborough
2002 - 2004
City College, Birmingham
1999-2001
Stoke Technical College, Stoke-on-Trent
|
School Education
Bishop Vesey Grammar School
Sutton Coldfield, West Midlands
|
|
|
|
PERSONAL INTERESTS
Qualified FA Football Coach Level 1
Golf Mostly social and business
|
|
|
REFERENCES
Mr Bruce Carter (Area Commercial Manager)
Balfour Kilpatrick Ltd West Region
0121 503 8850 (bruce.carter@balfourkilpatrick.com)
Mr Carl Banks (Senior Project Manager)
Balfour Kilpatrick Ltd West Region
0121 503 8850 (carl.banks@balfourkilpatrick.com)
|
|
|
PROJECT EXPERIENCE
|
Walsall College
Role: Senior Quantity Surveyor
Project Duration: 5 months pre-construction, 12 months construction
Project Value: £10.7m
|
A £38m new build technical college on a brown field city centre site comprising of design and build installation
Electrical Substation, lighting, small power, (plug and play modular system), fire, security, data, bms, disabled toilet and refuge, UPS
Mechanical Displacement ventilation, chilled beams, dx cooling, DHWS/CWS, prefabricated plant rooms and gas systems
Project role consisted of leading a team of surveyors to achieve control of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting
|
|
BT Stadium House, Cardiff
Role: Project Quantity Surveyor
Project Duration: 6 months construction
Project Value: £1.8m
|
An existing data centre strip out and refurbishment for BT, acting as main contractor including builderswork strip out, new walls/partitions, ceilings, forming new risers and raised floors, electrical strip out, new lighting, containment, power supplies, UPS and Power Distribution units, fire and security alarm systems and mechanical items strip out, new close cooling units, supply and extract ventilation and gas suppression systems
Project role consisted of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting
|
IDC/BT Data Centre, Cardiff
Role: Project Quantity Surveyor
Project Duration: 9 months construction
Project Value: £3.8m
|
An existing data centre, with an existing empty hall ready for fit out for BT, acting as main contractor including builderswork strip out, new walls/partitions, ceilings, forming new risers and raised floors, electrical strip out, new lighting, containment, power supplies, UPS and Power Distribution units, fire and security alarm systems and mechanical items strip out, new close cooling units, supply and extract ventilation and gas suppression systems
Project role consisted of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting
|
|
Basepoint Centre for Innovation, Luton
Role: Project Quantity Surveyor
Project Duration: 14 months construction
Project Value: £2.2m
|
A new build site for a two storey building with reception area, workshops, meeting rooms and office consisting electrical new intelligent lighting systems, containment, localised sub-station, power supplies including underfloor busbar, fire and security alarm systems and mechanical items solar powered water heating systems, natural ventilation, night purge extract ventilation and DH&CWS
Project role consisted of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting.
|
|
Motor Transport Workshop, Shrewsbury
Role: Project Quantity Surveyor
Project Duration: 6 months construction
Project Value: £0.4m
|
A new build site for a motor transport workshop consisting of lighting, small power, fire and security alarm systems, DH&CWS and heating systems
Project role consisted of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting.
|
|
|
|
PROJECT EXPERIENCE
|
CTMP, Shrewsbury
Role: Project Quantity Surveyor
Project Duration: 6 months construction
Project Value: £0.3 m
|
An existing court room (listed building), requiring strip out and refurbishment, acting as main contractor including builderswork strip out, new walls/partitions, ceilings, forming new risers and raised floors, electrical strip out, new lighting, containment, power supplies, UPS, fire and security alarm systems and mechanical items strip out, new close cooling units, supply and extract ventilation and gas suppression systems
Project role consisted of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting.
|
|
B5 Southside, Birmingham
Role: Assistant Quantity Surveyor
Project Duration: 24 months construction
Project Value: £5.0 m
|
A new build site for 461 nr one and two bedroom city centre apartments consisting of lighting, small power, fire and security alarm systems, DH&CWS and heating systems
Project role consisted of sub-contract accounts from placing of orders to final accounts, contract and tender sum negotiations and financial reporting to the Senior Project QS.
|
|
|